F
fims-issue-traceability
Initiate Technical Engagement with OGD for Systems Integration
#200
· created
May 25, 2026
by
projects ictpack
3. System development
A: status:: inprogress
B: priority:: high-Must Do (non-negotiable for your workflow)
F: Raised-At-Stage:: Inception
H: Owner:: TIT
updated
May 25, 2026
Infrastructure Readiness Staging and Production environment
#199
· created
May 25, 2026
by
Mussa Shomari
6. Piloting, data migration and deployment of the enhancements
Jun 16, 2026
A: status:: inprogress
B: priority:: high-Must Do (non-negotiable for your workflow)
F: Raised-At-Stage:: Inception
H: Owner:: TIT
updated
May 26, 2026
Provide environment for source code management and CI/CD
#198
· created
May 25, 2026
by
Mussa Shomari
3. System development
Aug 31, 2025
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
F: Raised-At-Stage:: Inception
H: Owner:: TIT
updated
May 25, 2026
Resolved Test Cases: An updated set of test cases that specifically address the gaps identified in the initial FAT, ensuring they are aligned with the actual system workflows.
#195
· created
May 25, 2026
by
projects ictpack
7. Documentation
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: QA
H: Owner:: ICTPACK
updated
May 25, 2026
Role-Based Access Control (RBAC) Matrix: A formal document defining every user role (e.g., Administrator, Senior Officer,Officer, Director General) and their specific permissions (Create, Read, Update, Delete) for every module.
#194
· created
May 25, 2026
by
projects ictpack
7. Documentation
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: QA
H: Owner:: ICTPACK
1
updated
May 26, 2026
Preliminary Security Scan: Evidence that a basic vulnerability scan has been performed and that "Critical" and "High" severity issues related to unauthorized access or data exposure have been patched.
#192
· created
May 25, 2026
by
Mussa Shomari
Jun 15, 2026
A: Status:: new
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: QA
H: Owner:: TIT
updated
May 26, 2026
System Health Check: Confirmation that all core services (database, API gateways, external integrations) are operational and accessible via the Commission's network/VPN as required.
#190
· created
May 25, 2026
by
projects ictpack
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: QA
H: Owner:: TIT
updated
May 25, 2026
Sanitized Sample Data: The environment must be pre-loaded with sufficient, realistic sample data to allow for end-to-end testing of complex workflows (e.g., merger from filing to closure).
#189
· created
May 25, 2026
by
projects ictpack
A: status:: in-triage
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
G: Source:: QA
H: Owner:: ICTPACK
updated
May 25, 2026
Dedicated Test Environment: Delivery of a stable, "frozen" test environment that mirrors the production environment. This environment must be independent of the development branch to ensure no code changes occur during the testing window.
0 of 1 checklist item completed
#188
· created
May 25, 2026
by
projects ictpack
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: QA
H: Owner:: TIT
updated
May 25, 2026
Developer should keep track of the Risk Register, regularly review and that appropriate mitigation measures be implemented in a timely manner to manage identified risks.”
#187
· created
May 25, 2026
by
projects ictpack
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: QA
H: Owner:: ICTPACK
updated
May 25, 2026
Enhance the system to include essential missing functionalities, such as bulk data import and export capabilities as specified in the requirement document
0 of 3 checklist items completed
#180
· created
May 25, 2026
by
projects ictpack
Jun 15, 2026
A: status:: in-triage
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: PO
H: Owner:: ICTPACK
updated
May 26, 2026
Mandate active participation and ownership by business process owners and the PIT in reviewing and approving test cases prior to test execution.
0 of 2 checklist items completed
#178
· created
May 25, 2026
by
projects ictpack
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: QA
H: Owner:: TIT
updated
May 25, 2026
Enforce strict timelines with milestone tracking and clear accountability for all project deliverables.
#176
· created
May 25, 2026
by
projects ictpack
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
G: Source:: QA
H: Owner:: ICTPACK
updated
May 25, 2026
Establish a formal communication protocol with clearly defined channels, regular progress updates, and structured escalation procedures among the Developer, PIT, and QA teams.
2 of 3 checklist items completed
#175
· created
May 25, 2026
by
projects ictpack
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: FAT
H: Owner:: ICTPACK
H: Owner:: TIT
updated
May 26, 2026
Missing File Upload Requirements
#174
· created
May 09, 2026
by
Mussa Shomari
A: status:: Awaiting Closure - by source
C: type:: recommendation
D: Microservice:: Corporate Service
E: Service:: Finance & Accounts
F: Raised-At-Stage:: UI/UX
G: Source:: QA
H: Owner:: ICTPACK
updated
May 27, 2026
6. Missing Home Navigation for external users
#171
· created
May 09, 2026
by
Mussa Shomari
A: status:: inprogress
B: priority:: medium - Should Do (strongly recommended)
C: type:: recommendation
F: Raised-At-Stage:: UI/UX
G: Source:: QA
H: Owner:: ICTPACK
updated
May 25, 2026
Revenue
#169
· created
Apr 15, 2026
by
Mussa Shomari
D: Microservice:: Corporate Service
E: Service:: Finance & Accounts
F: Raised-At-Stage:: FAT
G: Source:: PO
H: Owner:: ICTPACK
updated
May 26, 2026
[UI/UX] Budget officer field requires manual entry leading to inconsistencies.
#162
· created
Apr 08, 2026
by
Mussa Shomari
2. Wireframes and Mock-ups (UI /UX)
Apr 21, 2026
F: Raised-At-Stage:: UI/UX
G: Source:: PO
H: Owner:: ICTPACK
updated
May 25, 2026
[UI/UX] Branding materials and institutional assets are not centralized.
#160
· created
Apr 08, 2026
by
Mussa Shomari
2. Wireframes and Mock-ups (UI /UX)
Apr 21, 2026
A: status:: in-triage
D: Micoservice: Public Relations Communication
F: Raised-At-Stage:: UI/UX
G: Source:: PO
H: Owner:: ICTPACK
updated
May 25, 2026
[UI/UX] TV and Radio programs are not clearly separated in the UI.
#159
· created
Apr 08, 2026
by
Mussa Shomari
2. Wireframes and Mock-ups (UI /UX)
Apr 21, 2026
A: status:: in-triage
D: Micoservice: Public Relations Communication
F: Raised-At-Stage:: UI/UX
G: Source:: PO
H: Owner:: ICTPACK
updated
May 25, 2026
1
2
3
4